A SOW is only useful if it's specific. 'Electrical per plans' isn't a scope; it's a placeholder that turns into an argument the first time a plan detail is ambiguous. A real scope of work names the trade's inclusions, exclusions, and the boundary where their work ends and the next trade's begins.
Verbal or emailed scope agreements are common on smaller jobs and are exactly where disputes come from later — one side remembers 'run wire for an outlet' as including the outlet, the other doesn't, and there's nothing written to settle it.
Example
A GC sends a painter a one-line scope: 'paint interior.' Three weeks in, the painter says trim isn't included; the GC says it obviously is. A written SOW naming rooms, surfaces, and finish level would have settled it before the first coat went on.