01
Contract reference
Project, original agreement, change-order number, and date.
A change order is a signed, priced amendment to a construction contract that adds, removes, or modifies scope, cost, or schedule after work is already under contract.
Direct answer
A construction change order is a written agreement that modifies the contracted work, contract sum, contract time, or a combination of the three. A complete change order identifies the contract and change, states the price and schedule effect, and records authorization by the parties required under that contract.
01
Project, original agreement, change-order number, and date.
02
A specific description of what is added, removed, or revised and why.
03
The agreed increase, decrease, or no-change statement for the contract sum.
04
Added or removed days, revised milestone, or an explicit no-change statement.
05
Names, roles, dates, and signatures required by the governing contract.
Industry standard
AIA Contract Documents — change-order fundamentalsThe distinction between an agreed change order and other change instruments, including scope, price, time, and authorization.
Industry standard
AIA Contract Documents — G701 Change OrderThe standard G701 record for an agreed adjustment to the work, contract sum, and contract time.
Change procedures and signature authority come from the governing contract and applicable law. This completeness check is operational guidance, not legal advice.
Published July 21, 2026 · Sources verified August 4, 2026 · Research methodology
Nothing on a construction contract is fixed once the crew mobilizes. Plans get revised, owners ask for upgrades, field conditions turn up something nobody drew, and every one of those changes has to move through a change order before it's billable. A change order records what changed, what it costs, and who signed off — the three things a dispute always comes back to.
The format varies by contract type. AIA-based contracts use a formal change order form tied to the original agreement; smaller jobs might run on a one-page memo. What doesn't vary is the sequence: the change is identified, priced, and approved in writing before the work proceeds — not after.
A GC's electrician hits an unmarked gas line while trenching for a footing. The fix adds two days of hand-digging and a permit call. Before that work starts, the GC writes a change order pricing the extra labor and equipment, the owner signs it, and the crew proceeds — instead of the sub doing the work on a verbal 'yeah, go ahead' and fighting about the invoice a month later.
Verbal approval in the field is where the paper trail — and the margin — disappears.
“They do the work, tell the GC 'no problem,' and then send me a vague text or a blurry photo of a scribbled note 2 weeks later. By the time I write up the Change Order, the GC denies it because it wasn't documented in time.”
Where this shows up in Datumel:
We use first-party analytics cookies to improve Datumel. We use first-party cookies to understand how the site is used and to improve it. Nothing is shared with third-party ad networks. Privacy.