01
Origin
Link the RFI, drawing revision, field directive, owner request, or condition that triggered the change.
Subcontractors who need a formal change order memo the same day the field asks for extra work.
Actual template
This filled example shows the level of detail both editable templates ask for. Replace the example values, attach the backup, and route it through the notice and approval process in your subcontract.
Opens Google's copy screen in a new tab. Choose Make a copy to save an editable version to your Drive.
Change order request
COR-017
August 4, 2026
Description of change
Relocate two floor-box feeds from Grid C-4 to C-5 after the furniture-plan revision issued August 1. Includes rerouting conduit above Level 2, extending conductors, and re-testing both circuits.
Reason: Owner furniture revision after the original electrical rough-in layout was approved.
Status
Pending written authorization
Scope included
Scope excluded
| Cost item | Amount |
|---|---|
| Electrician labor | $1,440 |
| Material and consumables | $385 |
| Supervision and contract markup | $183 |
| Total proposed change | $2,008 |
Submission and authorization
Submitted by: Maya Chen, Project Manager — BrightLine Electrical
This request documents a proposed change. It becomes authorization only when approved as required by the governing contract.
Both templates include blank fields, a cost table, schedule impact, attachments, and authorization fields.
Or generate a memo from a description →Direct answer
Document a change order in one traceable record with five parts: project and request identifiers; the direction and contract reference; included and excluded scope; itemized labor, material, equipment, markup, and schedule impact; then backup and authorization. The filled example and blank Word and Google Sheets templates on this page show how those pieces fit together.
01
Link the RFI, drawing revision, field directive, owner request, or condition that triggered the change.
02
State inclusions, exclusions, location, quantities, and affected specification or drawing references.
03
Separate labor, materials, equipment, subcontract cost, tax, and contract-allowed markup.
04
Record added days, affected milestones, sequencing constraints, or no time impact.
05
Capture the authorized names, roles, decision, signature dates, and any not-to-exceed limit.
Industry standard
AIA Contract Documents — change-order fundamentalsThe distinction between an agreed change order and other change instruments, including scope, price, time, and authorization.
Institutional procedure
West Virginia University — construction change-order procedureInstitutional documentation controls for change authorization, labor, material, equipment, daily tickets, and supporting records.
The contract controls notice deadlines, markups, backup, signature authority, and whether work may start before a formal change order. Review those requirements for each project.
Published July 21, 2026 · Sources verified August 4, 2026 · Research methodology
The gap between 'sure, no problem' in the field and a signed change order is where subs lose the most money — not because the work wasn't real, but because nothing was written down before the GC had a chance to forget or dispute it.
“They do the work, tell the GC 'no problem,' and then send me a vague text or a blurry photo of a scribbled note 2 weeks later. By the time I write up the Change Order, the GC denies it because it wasn't documented in time.”
“I feel like we are bleeding cash on 'favors' that never get billed.”
What the field asked for, in your own words — no form-filling required.
Priced, scoped, and formatted for approval, not a text message that reads like a favor.
While the GC still remembers agreeing to it — not two weeks later when the story has changed.
Free, runs in your browser, no signup.
Change Order MemoFree
Describe the change in plain language. Get a formal CO memo ready to send for approval.
The tool catches it on one bid. The T&M Leak Audit ($1,499 one-time) finds the pattern across your process.
We use first-party analytics cookies to improve Datumel. We use first-party cookies to understand how the site is used and to improve it. Nothing is shared with third-party ad networks. Privacy.