Change order template for subcontractors

Subcontractors who need a formal change order memo the same day the field asks for extra work.

Actual template

See the template before you use it

This filled example shows the level of detail both editable templates ask for. Replace the example values, attach the backup, and route it through the notice and approval process in your subcontract.

Download editable Word templateOpen in Google Sheets

Opens Google's copy screen in a new tab. Choose Make a copy to save an editable version to your Drive.

Filled example — both templates include a blank versionWord + Google Sheets · US Letter

Change order request

North Harbor Office Renovation

COR-017

August 4, 2026

Subcontractor
BrightLine Electrical
General contractor
Cedar Ridge Builders
Contract reference
Electrical subcontract dated May 12, 2026
Requested by
Site superintendent — field direction FD-08

Description of change

Relocate two floor-box feeds from Grid C-4 to C-5 after the furniture-plan revision issued August 1. Includes rerouting conduit above Level 2, extending conductors, and re-testing both circuits.

Reason: Owner furniture revision after the original electrical rough-in layout was approved.

Status

Pending written authorization

Scope included

  • Remove and reroute approximately 42 LF of 3/4-inch EMT
  • Extend circuit conductors and reconnect two floor boxes
  • Label, test, and update the electrical as-built markup

Scope excluded

  • Concrete cutting or floor-box relocation by others
  • Work outside Level 2, Area C
Proposed change cost breakdown
Cost itemAmount
Electrician labor$1,440
Material and consumables$385
Supervision and contract markup$183
Total proposed change$2,008
Schedule impact
No change to substantial completion if approved by August 6. Work requires one return shift before ceiling close-in.
Attachments
FD-08, revised furniture plan A-621, field photos, labor/material backup

Submission and authorization

Submitted by: Maya Chen, Project Manager — BrightLine Electrical

Authorized signature / role
Date

This request documents a proposed change. It becomes authorization only when approved as required by the governing contract.

Both templates include blank fields, a cost table, schedule impact, attachments, and authorization fields.

Or generate a memo from a description →

Direct answer

How should contractors document change orders?

Document a change order in one traceable record with five parts: project and request identifiers; the direction and contract reference; included and excluded scope; itemized labor, material, equipment, markup, and schedule impact; then backup and authorization. The filled example and blank Word and Google Sheets templates on this page show how those pieces fit together.

Operational completeness check

01

Origin

Link the RFI, drawing revision, field directive, owner request, or condition that triggered the change.

02

Scope boundary

State inclusions, exclusions, location, quantities, and affected specification or drawing references.

03

Cost support

Separate labor, materials, equipment, subcontract cost, tax, and contract-allowed markup.

04

Schedule effect

Record added days, affected milestones, sequencing constraints, or no time impact.

05

Approval record

Capture the authorized names, roles, decision, signature dates, and any not-to-exceed limit.

Sources and verification

The contract controls notice deadlines, markups, backup, signature authority, and whether work may start before a formal change order. Review those requirements for each project.

Published July 21, 2026 · Sources verified August 4, 2026 · Research methodology

The gap between 'sure, no problem' in the field and a signed change order is where subs lose the most money — not because the work wasn't real, but because nothing was written down before the GC had a chance to forget or dispute it.

They do the work, tell the GC 'no problem,' and then send me a vague text or a blurry photo of a scribbled note 2 weeks later. By the time I write up the Change Order, the GC denies it because it wasn't documented in time.

I feel like we are bleeding cash on 'favors' that never get billed.

How it works

01

Describe the change in plain language

What the field asked for, in your own words — no form-filling required.

02

Get a formal CO memo ready to send

Priced, scoped, and formatted for approval, not a text message that reads like a favor.

03

Send it the same day

While the GC still remembers agreeing to it — not two weeks later when the story has changed.

Next step

Free, runs in your browser, no signup.

Change Order MemoFree

Describe the change in plain language. Get a formal CO memo ready to send for approval.

Open →

Beyond this page

The tool catches it on one bid. The T&M Leak Audit ($1,499 one-time) finds the pattern across your process.