Construction change directive (CCD)

A construction change directive (CCD) is a written order from the owner or architect to proceed with changed work immediately, used when there's no time to agree on price before the work must start.

A CCD exists for the moments a change order process is too slow for the job. The owner or architect directs the work to proceed now, with cost and schedule impact to be determined and agreed afterward — usually converting into a formal change order once the numbers are worked out.

The risk sits with whoever performs the work under a CCD: they're obligated to proceed on a directive that doesn't yet have an agreed price, which means the pricing conversation happens after the cost is already locked in, not before.

Example

An owner needs a structural change made immediately to keep a schedule from slipping further, before the GC and structural engineer have finished pricing it. The architect issues a CCD directing the GC to proceed; the price gets negotiated over the following two weeks and converts into a standard change order.

Next step

Where this shows up in Datumel:

Change Order MemoFree

Describe the change in plain language. Get a formal CO memo ready to send for approval.

Open →

Change Order Audit$9,999 one-time

A review of your change order documentation and dispute exposure. Finds where approvals slip through verbal exchanges.

Open →